Skip to content
  • Categories
  • Recent
  • Tags
  • Popular
  • World
  • Users
  • Groups
Skins
  • Light
  • Cerulean
  • Cosmo
  • Flatly
  • Journal
  • Litera
  • Lumen
  • Lux
  • Materia
  • Minty
  • Morph
  • Pulse
  • Sandstone
  • Simplex
  • Sketchy
  • Spacelab
  • United
  • Yeti
  • Zephyr
  • Dark
  • Cyborg
  • Darkly
  • Quartz
  • Slate
  • Solar
  • Superhero
  • Vapor

  • Default (No Skin)
  • No Skin
Collapse
Code Project
  1. Home
  2. The Lounge
  3. How Would You Handle This?

How Would You Handle This?

Scheduled Pinned Locked Moved The Lounge
csharpcsswpfquestioncareer
38 Posts 20 Posters 0 Views 1 Watching
  • Oldest to Newest
  • Newest to Oldest
  • Most Votes
Reply
  • Reply as topic
Log in to reply
This topic has been deleted. Only users with topic management privileges can see it.
  • Z Offline
    Z Offline
    zephaneas
    wrote on last edited by
    #1

    I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

    D P E D M 13 Replies Last reply
    0
    • Z zephaneas

      I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

      D Offline
      D Offline
      dan sh
      wrote on last edited by
      #2

      I would personally choose one of them. Working close to 70 hours a week is killing. I know cause I am doing for quiet a while now. But then, your life, your job, your choices.

      "Bastards encourage idiots to use Oracle Forms, Web Forms, Access and a number of other dinky web publishing tolls.", Mycroft Holmes[^]

      1 Reply Last reply
      0
      • Z zephaneas

        I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

        P Offline
        P Offline
        Pete OHanlon
        wrote on last edited by
        #3

        So you expect people in company B to work their hours to suit you? If you can't work to their hours, then how do you expect them to be able to impart things to you? You need to make a choice here.

        *pre-emptive celebratory nipple tassle jiggle* - Sean Ewington

        "Mind bleach! Send me mind bleach!" - Nagy Vilmos

        CodeStash - Online Snippet Management | My blog | MoXAML PowerToys | Mole 2010 - debugging made easier

        Z 1 Reply Last reply
        0
        • Z zephaneas

          I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

          E Offline
          E Offline
          Ennis Ray Lynch Jr
          wrote on last edited by
          #4

          Company A is the priority. Tell Company B that. Inform them that you will be available from (and give a reasonable availability for meetings during work hours) but will perform the work at your own set schedule. Company B, already sounds unreasonable, since, after hiring you and knowing your situation, and committing you to a very unreasonable phased payment approach, they are also, now, demanding even more from you. I hope Company B is putting the money for your payment in escrow.

          Need custom software developed? I do custom programming based primarily on MS tools with an emphasis on C# development and consulting. I also do Android Programming as I find it a refreshing break from the MS. "And they, since they Were not the one dead, turned to their affairs" -- Robert Frost

          Z 1 Reply Last reply
          0
          • Z zephaneas

            I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

            D Offline
            D Offline
            Dr Walt Fair PE
            wrote on last edited by
            #5

            I would tell Company B that if they want you to give them priority, then they need to pay you 40 hrs/week with pay checks every 2 weeks. If they can't or won't do that, then what they need is a part time worker and that's what they already have. As my grandfather used to say: (in a thick German accent) "You can sh*t in one hand and 'want' in the other and see which hand fills up first." Now, if you want to keep both gigs going, then work out a compromise. Perhaps give them 1 set day per week for meetings you will attend. You know the situation better than anyone else, but those are the things I would consider.

            CQ de W5ALT

            Walt Fair, Jr., P. E. Comport Computing Specializing in Technical Engineering Software

            R 1 Reply Last reply
            0
            • Z zephaneas

              I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

              M Offline
              M Offline
              Marc Clifton
              wrote on last edited by
              #6

              Well, since the work with B is paid at the end of each phase (I'm assuming there's some sort of agreement on what the work is that makes up a phase) it seems that what is relevant is whether you get the work done by the scheduled date. However, if getting the work done does require interacting on a regular basis and working with other people's schedule, then you'll need to figure out how to accommodate their needs as part of your responsibility for the contract your engaged in. It does seem to me though that you should have, during the negotiations, clearly pointed out that you would not be able to accommodate their meeting schedule - this would have given them more information to make a decision about whether to work with you, and if they didn't budge, it would have made it clearer that you probably shouldn't have accepted the work. So in the end, one or the other needs to give or be renegotiated. Marc

              Reverse Engineering Legacy Applications
              How To Think Like a Functional Programmer
              My Blog
              Computational Types in C# and F#

              1 Reply Last reply
              0
              • Z zephaneas

                I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

                Mike HankeyM Offline
                Mike HankeyM Offline
                Mike Hankey
                wrote on last edited by
                #7

                Did you tell company B that you were working for company A currently? If so they should realize and appreciate that you are still obligated to A. If not you might try cloning or dazzle them with bullshit cause you created a potential mess.

                VS2010/Atmel Studio 6.0 ToDo Manager Extension
                Version 3.0 now available. There is no place like 127.0.0.1

                C 1 Reply Last reply
                0
                • Z zephaneas

                  I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

                  A Offline
                  A Offline
                  Andrew Rissing
                  wrote on last edited by
                  #8

                  My questions would be: a) Did you inform Company B that you're currently working a contract full-time? b) If so, did they/you negotiate that you were going to be available after Company A's contract ended? c) Did Company B change their plans after the fact? d) Can you reschedule Company A to work at varying times, so that you can still satisfy both?

                  Z 1 Reply Last reply
                  0
                  • Z zephaneas

                    I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

                    J Offline
                    J Offline
                    jesarg
                    wrote on last edited by
                    #9

                    First, I hope you know what you're doing with a 70-hour work week, as most mortals can't possibly hope to handle it. Second, the situation is something you should have forseen when you signed with Company B, and you should have made it clear which hours you would and would not be available. If you've already agreed on the hours and they try to change it, you need to tell them that it requires a renegociation.

                    1 Reply Last reply
                    0
                    • Z zephaneas

                      I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

                      J Offline
                      J Offline
                      jschell
                      wrote on last edited by
                      #10

                      zephaneas wrote:

                      They have started sending me meeting invites that conflict with this day job at Company A.

                      So refuse the invite and propose an alternative time: early morning, evening or lunch.

                      1 Reply Last reply
                      0
                      • Z zephaneas

                        I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

                        P Offline
                        P Offline
                        Paul Conrad
                        wrote on last edited by
                        #11

                        I would probably stick with working for just Company A. As the others have posted, 70 hour per week can be grueling. If you are up to working 70 hours a week and you can do it without getting burned out, it is your choice. I am not sure about Company B as they sound like they might be unreasonable.

                        "Any sort of work in VB6 is bound to provide several WTF moments." - Christian Graus

                        1 Reply Last reply
                        0
                        • P Pete OHanlon

                          So you expect people in company B to work their hours to suit you? If you can't work to their hours, then how do you expect them to be able to impart things to you? You need to make a choice here.

                          *pre-emptive celebratory nipple tassle jiggle* - Sean Ewington

                          "Mind bleach! Send me mind bleach!" - Nagy Vilmos

                          CodeStash - Online Snippet Management | My blog | MoXAML PowerToys | Mole 2010 - debugging made easier

                          Z Offline
                          Z Offline
                          zephaneas
                          wrote on last edited by
                          #12

                          Pete O'Hanlon wrote:

                          So you expect people in company B to work their hours to suit you?

                          Not sure how you came up with that, as I never said or implied that. This is a remote, task based project that I can work on at my leisure. They just prefer that I be available during the day. The whole reason for the post was that they now seem to be pushing me to give up my day job & do their project during the day. I want to find a tactful way to so no.

                          P 1 Reply Last reply
                          0
                          • E Ennis Ray Lynch Jr

                            Company A is the priority. Tell Company B that. Inform them that you will be available from (and give a reasonable availability for meetings during work hours) but will perform the work at your own set schedule. Company B, already sounds unreasonable, since, after hiring you and knowing your situation, and committing you to a very unreasonable phased payment approach, they are also, now, demanding even more from you. I hope Company B is putting the money for your payment in escrow.

                            Need custom software developed? I do custom programming based primarily on MS tools with an emphasis on C# development and consulting. I also do Android Programming as I find it a refreshing break from the MS. "And they, since they Were not the one dead, turned to their affairs" -- Robert Frost

                            Z Offline
                            Z Offline
                            zephaneas
                            wrote on last edited by
                            #13

                            Ennis Ray Lynch, Jr. wrote:

                            and committing you to a very unreasonable phased payment approach

                            There's noting unreasonable at all about the pay approach. This is typical of fixed rate projects. You break it into phases, and at the end of each phase you invoice them & get paid.

                            E pkfoxP 2 Replies Last reply
                            0
                            • A Andrew Rissing

                              My questions would be: a) Did you inform Company B that you're currently working a contract full-time? b) If so, did they/you negotiate that you were going to be available after Company A's contract ended? c) Did Company B change their plans after the fact? d) Can you reschedule Company A to work at varying times, so that you can still satisfy both?

                              Z Offline
                              Z Offline
                              zephaneas
                              wrote on last edited by
                              #14

                              a) yes b) yes c) I think that's what they're hoping for d) I asked, and they said now, as they have had 6 other contractors come in before me and got burned. When I asked, they came back the next day & said that they really like my work and are happy with me, but they want me in the office for the duration of the project.

                              pkfoxP 1 Reply Last reply
                              0
                              • Z zephaneas

                                Pete O'Hanlon wrote:

                                So you expect people in company B to work their hours to suit you?

                                Not sure how you came up with that, as I never said or implied that. This is a remote, task based project that I can work on at my leisure. They just prefer that I be available during the day. The whole reason for the post was that they now seem to be pushing me to give up my day job & do their project during the day. I want to find a tactful way to so no.

                                P Offline
                                P Offline
                                Pete OHanlon
                                wrote on last edited by
                                #15

                                zephaneas wrote:

                                Not sure how you came up with that, as I never said or implied that.

                                They are setting up meetings at times that are convenient to them. The only alternative, for them, is to have meetings that are convenient to you. There's an implication there that the times won't be convenient for them. And of course they'd prefer that you were available during the day - after all, that's most likely when they are available. Suppose they have questions; when do you think you should answer them?

                                *pre-emptive celebratory nipple tassle jiggle* - Sean Ewington

                                "Mind bleach! Send me mind bleach!" - Nagy Vilmos

                                CodeStash - Online Snippet Management | My blog | MoXAML PowerToys | Mole 2010 - debugging made easier

                                Z 1 Reply Last reply
                                0
                                • Z zephaneas

                                  Ennis Ray Lynch, Jr. wrote:

                                  and committing you to a very unreasonable phased payment approach

                                  There's noting unreasonable at all about the pay approach. This is typical of fixed rate projects. You break it into phases, and at the end of each phase you invoice them & get paid.

                                  E Offline
                                  E Offline
                                  Ennis Ray Lynch Jr
                                  wrote on last edited by
                                  #16

                                  But I have thirty grand in unpaid invoices from before I learned better. That is almost a down payment on a nice sports car. Typical, btw, is in the eye of the beholder. I would require half up front, and then milestone payments. But then, I no longer do fixed projects. Not worth it.

                                  Need custom software developed? I do custom programming based primarily on MS tools with an emphasis on C# development and consulting. I also do Android Programming as I find it a refreshing break from the MS. "And they, since they Were not the one dead, turned to their affairs" -- Robert Frost

                                  Z _ 2 Replies Last reply
                                  0
                                  • Mike HankeyM Mike Hankey

                                    Did you tell company B that you were working for company A currently? If so they should realize and appreciate that you are still obligated to A. If not you might try cloning or dazzle them with bullshit cause you created a potential mess.

                                    VS2010/Atmel Studio 6.0 ToDo Manager Extension
                                    Version 3.0 now available. There is no place like 127.0.0.1

                                    C Offline
                                    C Offline
                                    Colin Mullikin
                                    wrote on last edited by
                                    #17

                                    Mike Hankey wrote:

                                    If not you might try cloning or dazzle them with bullsh*t cause you created a potential mess.

                                    This gave me a good laugh. :thumbsup:

                                    The United States invariably does the right thing, after having exhausted every other alternative. -Winston Churchill America is the only country that went from barbarism to decadence without civilization in between. -Oscar Wilde Wow, even the French showed a little more spine than that before they got their sh*t pushed in.[^] -Colin Mullikin

                                    1 Reply Last reply
                                    0
                                    • Z zephaneas

                                      I am working on a hourly rate contract job with Company A that's going to run until the end of March. It's 40 hrs a week. I also just signed a fixed rate 6 month DOS to WPF conversion contract with Company B. The folks at company B have indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Thing is, the gig with Company A is 40 hours a week, and I get paid every other week. The gig with Company B is only 25-30 hours a week and I get paid at the end of each phase. I'm ok with the pay arrangements because I get both regular pay and a fat check at the end of each phase. Each phase runs 4-6 weeks. I like both gigs, and the people at both. I get alone well with all of them. But I need to communicate to the people at Company B that it's unreasonable to stop working for Company A for less hours and less frequent pay. How would you handle this? What would you say? Thanks

                                      C Offline
                                      C Offline
                                      charlieg
                                      wrote on last edited by
                                      #18

                                      You're getting good advice here. Remember that this arrangement is a two way street, and they don't own you. Be professional, but don't be afraid to push back. Now, the OP has some stuff in it that worries me: indicated that they would like me to put in 25-30 a week. It's remote so I can work on it whenever I want, however, they made it clear during negotiations that they would really like me to make this a priority and be available during the days. They have even said they wanted me to phase out the other job with Company A. They have started sending me meeting invites that conflict with this day job at Company A. I'm a contractor here, so I can take the day off, but I don't get paid for it. Do you see the problem? What is in the contract? Who is your contract contact? You need to have a heart to heart right now to clarify the situation. As another has a grandfather who so eloquently phrased the situation... if they want you full time, and at their whim, that will cost more.

                                      Charlie Gilley You're going to tell me what I want to know, or I'm going to beat you to death in your own house. "Where liberty dwells, there is my country." B. Franklin, 1783 “They who can give up essential liberty to obtain a little temporary safety deserve neither liberty nor safety.” BF, 1759

                                      1 Reply Last reply
                                      0
                                      • P Pete OHanlon

                                        zephaneas wrote:

                                        Not sure how you came up with that, as I never said or implied that.

                                        They are setting up meetings at times that are convenient to them. The only alternative, for them, is to have meetings that are convenient to you. There's an implication there that the times won't be convenient for them. And of course they'd prefer that you were available during the day - after all, that's most likely when they are available. Suppose they have questions; when do you think you should answer them?

                                        *pre-emptive celebratory nipple tassle jiggle* - Sean Ewington

                                        "Mind bleach! Send me mind bleach!" - Nagy Vilmos

                                        CodeStash - Online Snippet Management | My blog | MoXAML PowerToys | Mole 2010 - debugging made easier

                                        Z Offline
                                        Z Offline
                                        zephaneas
                                        wrote on last edited by
                                        #19

                                        Pete O'Hanlon wrote:

                                        Suppose they have questions; when do you think you should answer them?

                                        Um, when they ask? I didn't say I wasn't available during the day. I said I wouldn't be working their project during the day.

                                        P 1 Reply Last reply
                                        0
                                        • E Ennis Ray Lynch Jr

                                          But I have thirty grand in unpaid invoices from before I learned better. That is almost a down payment on a nice sports car. Typical, btw, is in the eye of the beholder. I would require half up front, and then milestone payments. But then, I no longer do fixed projects. Not worth it.

                                          Need custom software developed? I do custom programming based primarily on MS tools with an emphasis on C# development and consulting. I also do Android Programming as I find it a refreshing break from the MS. "And they, since they Were not the one dead, turned to their affairs" -- Robert Frost

                                          Z Offline
                                          Z Offline
                                          zephaneas
                                          wrote on last edited by
                                          #20

                                          Ennis Ray Lynch, Jr. wrote:

                                          But I have thirty grand in unpaid invoices from before I learned better

                                          That's a collection issue, not a payment schedule issue. if my clients miss a payment, I sstop working, and they know it before i ever start.

                                          1 Reply Last reply
                                          0
                                          Reply
                                          • Reply as topic
                                          Log in to reply
                                          • Oldest to Newest
                                          • Newest to Oldest
                                          • Most Votes


                                          • Login

                                          • Don't have an account? Register

                                          • Login or register to search.
                                          • First post
                                            Last post
                                          0
                                          • Categories
                                          • Recent
                                          • Tags
                                          • Popular
                                          • World
                                          • Users
                                          • Groups